January 14, 2008
Many of our customers have inquired about the time lengths
and current requirements in regards to obtaining a permit.
Below you will find the general requirements and time
lengths from each jurisdiction.
Once we receive your work order, Traffic Engineering
Services needs one day to do an onsite visit to your project
(for measurements, number of lanes, parking meters, etc.), a
second day is needed to draw the traffic control plan, and a
third day is required to package and submit the project.
| DISTRICT OF
COLUMBIA |
| |
|
| |
Closures |
| |
|
| |
All closures must be approved by
the Fire Marshal prior to being submitted to TSA. As
of last week, the Fire Marshal is saying that their
approval process will take 5-7 business days from
the date of submittal. I have attached a copy of the
email sent to all of our clients regarding this new
change. Once the Fire Marshal has approved the
traffic control plan, the project is then submitted
to TSA. TSA requires up to two weeks from the date
of submittal for approval. Therefore, from the day
we receive your project, it may take up to three
weeks for approval. |
| |
|
| |
Lane Closures |
| |
|
| |
Lane closures do not have to be
approved by the Fire Marshal or TSA. From the day we
receive your work order, we typically can obtain a
lane closure permit in 5-7 business days. |
| |
|
| |
After Hours Permits |
| |
|
| |
After Hours Permits are required
for any work being performed before 9:00am or after
3:30pm, Monday through Friday. They are also
required for any work being performed on Saturdays
prior to 7:00am or after 7:00pm. They are also
required for any work that is to be performed on
Sundays. Currently, the District of Columbia is
requiring a letter from the building owner stating
why there is a need to perform the work outside of
the regular working hours. |
| |
|
| BALTIMORE |
| |
|
| |
The City of Baltimore requires a
minimum of 5 business days for approval of a permit
from the date of submittal. They typically will only
approve full road closures for weekend work. They
require the building owner’s name and address. |
| |
|
| ALEXANDRIA |
| |
|
| |
The City of Alexandria generally
requires 3-5 business days for approval from the
date of submittal. They do not allow work to be
performed prior to 9:00am unless a noise variance
permit is applied for. They do not allow any work to
be performed on Sundays. |
| |
|
| ARLINGTON |
| |
|
| |
Arlington County generally takes 5
business days for an approval once the project has
been submitted. Arlington County also requires
police assistance for extensive closures. Arlington
County also requires the building owner’s
information on their application. A copy of this
application is enclosed. |
| |
|
| |
Click
here to download the Arlington permit application.
(PDF - 65KB) |
| |
|
| MONTGOMERY
COUNTY |
| |
|
| |
Montgomery County typically takes 2
weeks for approval once the project has been
submitted. They also require a certificate of
insurance listing Montgomery County as a certificate
holder. A sample certificate with their address is
enclosed. |
| |
|
| CITY OF
ROCKVILLE |
| |
|
| |
The City of Rockville generally
takes two weeks for approval from the date the
project was submitted. They also require a
certificate of insurance with the City of Rockville
listed as a certificate holder. In addition, they do
require a bond which the amount is determined once
the project has been submitted. They also require
the owner’s information and signature on the
application. A copy of this application is enclosed.
A sample insurance certificate with their address is
enclosed. |
| |
|
| |
Click
here to download the Rockville permit application.
(PDF - 197KB) |
Within the last month, we have implemented a new procedure
to help make our customers more aware of the status of their
pending project, and hopefully to eliminate them having to
call our office for an update. Each customer will be
receiving a daily email from our office stating the status
of each of their permits. If you do not receive the daily
email, please contact our office.
Once we receive your permit, we will fax a copy to your
office. If you do not receive your faxed copy, please
contact our office.
The best way to insure that your Traffic Control Plan and
Permit is correct is to fill out a permit work order
entirely and email it or fax it to our office. The more
detailed information your can provide, the better. If you
are on the road, or out of the office, we will be more then
happy to take the work order over the phone, but we prefer
to have the work order completed by the salesman. Please
include your email address on the bottom of the work order
so we can notify you of the status of your permit.
|